BASIC-DEMOS
Missile Defence Conference
BASIC and Demos hosted a Missile Defence Conference
in London on 9 November 2004.
Back to the main page on the
Conference
U.S. Missile Defense Update
Theresa Hitchens, Vice President, Center for Defense Information,
Washington DC.
First, thanks to BASIC and Demos for inviting me to participate
today, and thanks to all of you for taking the time to join in.
I've been asked to provide an update on the U.S. Missile Defense
Program.
As you know, President George W. Bush on Dec. 17, 2002, announced
that the United States intended to field an "initial" missile defense
capability - rather than simply a test bed as had previously been
stated -- within two to three years. He said, "We plan to begin
operating these initial capabilities in 2004 and 2005, and they
will include ground-based interceptors, sea-based interceptors,
additional Patriot (PAC-3) units, and sensors based on land, at
sea and in space."
We've less than two months to go in 2004. So, do we have or are
we nearing the capability to operate a missile defense system? Not
really. Indeed, a presidential or Pentagon announcement that the
GMD system was going on alert - long anticipated as taking place
at the end of October this year just prior to the Nov. 2 presidential
elections - has been put on hold.
Let's look at what has happened, and what hasn't.
Since July this year, five interceptors of the Ground-Based Midcourse
Defense System - the current centerpiece of the planned missile
defense architecture predicted by the Pentagon to cost about $25.3
billion to build -- have been placed in silos at Ft. Greely, Alaska.
MDA, in its original planning after the 2002 mandate, had hoped
to have nine in the ground by this time, followed by 10+ more at
Ft. Greely, four at Vandenberg, Calif., and 10 more at an "undisclosed"
third location by the end of 2005. It now looks like the 2005 schedule
is likely to stretch into 2006.
Further, the GMD interceptors buried under the frigid ground in
Alaska have never been flight tested. Indeed, the GMD program has
only tried to intercept a target eight times since testing began
in 1997 - with three failures. The most recent flight test - which
took place on Dec. 11, 2002, six days before President Bush's deployment
announcement - failed.
The tests that have been done up to now, however, involved fundamentally
different technology than that making up the interceptors at Ft.
Greely.
Missile defense interceptors consist of a two-stage booster rocket
tipped with a so-called kill vehicle, which is released in flight
and maneuvered toward a target ICBM in order to smash into it at
very high speeds. The Ft. Greely interceptors are based on a new
booster made by Orbital Sciences, which has never been tested to
see if it could successfully launch the kill vehicle. The earlier
tests used a slower, proven booster (and still had troubles - despite
the fact that the target was provided with an infrared homing beacon
that allowed the GMD interceptor to fix on it rather than have to
pick it out of clutter). This is significant because the higher
speeds of the new booster, more vibration will occur - vibration
that might affect the kill vehicle's sensitive sensors and other
components. And the back-up booster being made by Lockheed Martin
continues to face developmental problems that caused MDA to seek
out Orbital as an alternative in the first place.
In addition, the kill vehicle on the interceptors at Ft. Greely
also has new software for target identification that has never been
tested against a target.
Still, no intercept tests of the current interceptor configuration
are planned anytime soon. The next planned test, known as Integrated
Flight Test-13C, is not designed to see if the kill vehicle can
successfully fire and find its target, rather the test is aimed
at making sure components work together. And even that test has
been postponed several times since January due to computer glitches,
the latest MDA plan slates it for either later this month or sometime
in December. It remains unclear when an intercept test for the Ft.
Greely configuration will take place, as MDA and the Pentagon's
Office of Test & Evaluation are now involved in an effort to re-vamp
the GMD testing schedule.
Of course, an operational missile defense system comprises more
than just an interceptor. Sensors for finding, tracking and homing
in on incoming enemy ICBMs are critical - you can't hit what you
can't see. The truth is that the GMD interceptors at Ft. Greely
currently are essentially blind. The sensor suites planned - the
sea-based X-band radar needed to pick out the ICBM from any decoys
or debris as it whizzes through space, and a network of new early
warning satellites called the Space-Based Infrared System-High (SBIRS-High);
and new missile tracking satellites now known as the Space Tracking
and Surveillance System (STSS) - do not yet exist.
The $900-million X-band radar won't be available for integration
with the GMD system until next year at the earliest - it was supposed
to begin integration in 2003. Both the new satellite networks have
suffered technical difficulties, schedule delays and cost overruns
- and continue to suffer from congressional skepticism in the form
of budget cuts. The first Space Tracking and Surveillance System
satellite is now scheduled for launch sometime in 2007. The program,
formally named Space-Based Infrared System-Low (SBIRS-Low), was
launched in 1996 and at that time the first satellite was projected
to be launched in 2004. The program also has been substantially
dumbed down as well as slowed down, in that the first two satellites
of the STSS are based on old technology without the new capabilities
originally envisioned for the system, while the contractors work
on new technology development. Further, the final configuration
and cost of STSS are currently unknown - as the Missile Defense
Agency this year classified much of the program.
The Space-Based Infrared System-High has experienced even worse
problems, with costs jumping from the original 1996 estimate of
$3.6 billion (including ground facilities) to a currently projected
$10.2 billion. The first satellite, designed to go into a Highly
Elliptical Orbit, was delivered this year, 18 months late, and it
remains unclear when it will be launched. The follow-on effort to
put sister satellites into Geosynchronous Orbit is now is looking
to slip another two years from its most recently planned launch
date of 2006.
This leaves the GMD system dependent for the foreseeable on the
Cold War-era Cobra Dane radar based at Shemya, Alaska, which because
of its original mission of tracking incoming Soviet ICBMs, has little
capability to track any ICBMs emanating from North Korea. It also
means that the GMD system can't distinguish between decoys and/or
debris and actual warheads, meaning it is vulnerable to simple countermeasures.
In addition, the command and control system software to operate
the system is still in development and the latest iteration has
yet to be tested.
All of these problems lead to the delay in MDA's planned October
announcement that the system had been activated. The Pentagon's
informal goal since 2002 had been to announce "initial capability"
by Sept. 30 this year; with some DoD officials asserting that this
initial system would be 90 percent likely to knock down a North
Korean missile if one was launched at the United States. In recent
weeks, MDA has insisted that the goal was to begin "limited defensive
operations" sometime after December. Now, insiders are saying it
could be February before any capability can be stood up.
Another reason for the delay was that Northern Command, which is
to operate the system, and Strategic Command, which is designated
as the military's missile defense "advocate," have yet to figure
out the chain of command needed to run the GMD system. This is partly
a bureaucratic wrangle, but also there is serious concern at both
commands about the systems readiness. According to the Orlando Sentinel,
STRACOM officials "are so concerned about the effectiveness of the
new system that they have decided not to rely on it if a missile
attack appears imminent." "The system will not affect recommendations
given up the chain of command," one source told the paper, "That
means in STRATCOM's eyes, it's useless."
So, if GMD remains useless, what about the other pieces of the
layered missile defense network? Well, the best we can say is that
they are all at an immature state of development. The sea-based
Aegis Ballistic Missile Defense program also is facing interceptor
problems, and plans for fielding the initial configuration have
been cut back. Scheduling delays now call into question the Navy's
capability to fulfill even its less ambitious goal of equipping
two ships with initial variants of the SM-3 interceptor by the 2004/2005
timeframe for about $1.2 billion. The long-troubled Airborne Laser
(ABL) is teetering on the brink of cancellation, with the planned
"first light" of the laser itself once again being delayed from
this fall to likely no sooner than early next year due to problems
with the chemical fuel mix and the system for pumping it. Meanwhile,
the projected costs for the ABL have doubled to $5.1 billion, even
after MDA cut back its original goal of seven airplanes to one (a
second planned order was recently put on hold.) When ABL began in
1996, it was projected to have its first intercept test in 2002
and have planes flying in 2006. Under current plans, the first intercept
test is not slated until 2006 at the earliest. As for the space-based
interceptor system envisioned by MDA, only about $10 million has
been requested so far for technology development - although current
plans are to orbit three to six interceptors as a "test bed" in
2012. MDA has refused to provide cost estimates or any real parameters
for such a future system; meanwhile, the concept itself is controversial
among many in Congress who are concerned about the negative ramifications
of the United States becoming the first country to put weapons in
space.
MDA requested, and received from Congress, a total of $10.2 billion
in fiscal year 2005 for missile defense programs, and increase of
13 percent from the FY 04 request. A total of $53.1 billion is earmarked
for missile defense through FY 09. Up to this point, the United
States has spent about $90 billion pursuing missile defense since
Ronald Reagan launched his Star Wars effort. Despite this expenditure,
it currently remains impossible to predict when even a limited defensive
capability will be available.
|